|
But it still will not be British
|
|
Mandelson Defends Dome Decision
Peter Mandelson has defended the switching of a contentious contract for the
skin of the Millennium Dome roof from a German to an American company saying it
would transform the celebration venue into an "enduring legacy".
The new Teflon-coated glass fibre cladding will cost more than twice as much
as the planned PVC-coated polyester skin, but will extend the dome's life to at
least 25 years, giving the capital a lasting new landmark.
Mr Mandelson, the Minister without Portfolio who is responsible for the £250
million dome project, argued that the switch made sound sense even though the
original German contractors will have to be paid a six-figure sum in
compensation.
He said the Government had taken on board both environmentalists' concerns
about the materials being used and doubts, including those voiced by minister
Clare Short, about the value for money of a building whose original lifespan
was to have been between 10 and 15 years.
The BBC's Nick Robinson reports on the dome controversy
Dur: 3'21"
Earlier this week it emerged that Ms Short, the International Development
Secretary, criticised the original scheme as a "silly, temporary building" in
an interview given before the election.
|
Mandelson: 'I'm Teflon man'
|
|
Mr Mandelson confirmed that both he and the Deputy Prime Minister John Prescott
were aware on Monday, when the German firm's involvement sparked a political
row, of the possibility of a contractor switch.
Mr Prescott angered the British construction industry then by saying it was a "sad reflection" on their competency that no domestic firm could be found to fulfil the contract.
"He (Mr Prescott) knew that the option of switching the material from PVC to ... coated glass fibre was actively being sought, but we couldn't make an announcement until we knew that we had a secure supply of it and that we identified during the course of this week," said Mr Mandelson.
"Having been PVC Man, I am now Teflon Man," joked Mr Mandelson.
But the Conservatives cited the change of heart about the contract as evidence
of governmental confusion about the project. Shadow Culture, Media and Sport
minister Patrick Nicholls said the Government had performed a U-turn.
"Peter Mandelson's sudden U-turn over the contract to construct the roof of the Millennium Dome may have papered over his split with Clare Short, by extending the life of what she has called `a silly temporary building', but it leaves many unanswered questions," said Mr Nicholls.
"Clearly there can be two views on the dome. But a far more fundamental issue
is ministerial competence. That has been utterly lacking in this fiasco. To call
this lot a circus would be unkind to professional clowns," he said.
The New Millennium Experience Company is negotiating to
compensate Koch Hightex for their contract's cancellation.
The final figure is likely to be in six figures, although an NMEC spokesman
said he was surprised by some reports that it might be as high as £500,000.
Koch Hightex has warned that unless it was satisfied by the compensation
offer, it would consider litigation against NMEC.
"We are mystified as to what is happening and why the Government should now want to start again from
scratch with a new team and further delay to the project," said one of the company's directors, David Walker.
The company said that originally it tendered for both PVC/polyester and
PTFE/glass coatings - the latter being the Teflon option to which NMEC has now
switched.
It said its original Teflon tender would have cost less than the contract
which had now been signed with Birdair.
"We have been working on time for four months and could produce the Dome in
PTFE/glass as desired, since we are the world's biggest manufacturer," insisted
Mr Walker.
The German firm declined to comment on how much compensation it was seeking. However, it is understood that it may view its work on the project to date as
being worth £2 million or more.
|